The Construction of the National School for Administration
| Project Name | The Construction of the National School for Administration |
|---|---|
| Owner | Korea international Cooperation Agency |
| Donor | Korea international Cooperation Agency |
| Design Firm | Consolidated Consultants Engineering & Project Management |
| Supervision Firm | Al Ameed Architects & Engineers Co. |
| Start Date | June -2017 |
| Finish Date | April -2020 |
| Project Area | 5500 sqm |
Al-Mosleh & Atlantic Contracting Company executed the National School of Administration Project, which consists of a four-storey building. The ground floor includes an administration office, a multipurpose hall, a laboratory, and sanitary facilities, while the upper floors accommodate classrooms.
The company carried out excavation works and removal of debris to designated disposal sites, in addition to reinforced concrete works. The scope of finishing works included stone works, electrical and mechanical installations, plastering works, tiling works, painting works, suspended ceilings, and metal works comprising steel doors, the main external gate of the school, and handrails for the external staircases, along with glass works including glass façades.
As for the external works, they included the construction of perimeter boundary walls surrounding the building, a school cafeteria, a guard room, and the installation of an external school gate, in addition to the execution of pavements within the school yards and asphalt paving works for the external areas.
The project was executed in accordance with the approved engineering standards and the requirements of the Ministry of Education and Higher Education in Palestine.